118.4 miles from Depot Harbor

Description

Capacity of Passing Track 45 cars CNR-1926
Capacity of Other Tracks 38 cars CNR-1926
Engine Shed
Stalls 1 GTRB&B
Construction Frame GTRB&B
Roof Shingle GTRB&B
Water Station
Tank 14 1/2'x23' GTRB&B
Stand Pipe 6" Drop Pipe GTRB&B
Number of pipes 1 GTRB&B
Pump Northey GTRB&B
Steam Cylinder 6"x7" GTRB&B
Water Cylinder 4"x7" GTRB&B
Suction Pipe 3"x350' GTRB&B
Discharge Pipe 3" GTRB&B
Conduit Pipe 2"x40' GTRB&B
Source Madawaska R. GTRB&B
Remarks 52000 gal GTRB&B

History

Date Event Source Notes
1902-07-20 Whitney to Opeongo Lakes branch line under construction for St. Anthony Lumber Co. Leader p15
1902-11-26 Whitney to Opeongo lumber line completed after 15 months of labour. Cost: $200,000, 15 miles long. Trestles over 400 feet long. Leader p16

References